Altro commento, che prende in esame il comportamento anche piu' a lungo termine degli scavi.


There are cases in London clay that took at least 70 years for pore water pressure equilibration and reported failures of motorway cuts that took a large number of years before failure occurred. These have been published and are well known. Many of these have been shallow slipouts. The environment has alot to play in the case of cuts. From my experience, many failures take the form of surficial sloughs in cut slopes and generally occur within a year or two and much pronounced during or after wet seasons.

The 6 month time period provided by others has been used to define a period for temporary slopes using undrained analysis. Some factor of safety relation ship exists to incorporate the months excavation is to be left as temporary, with the FOS increasing with the time of temporary slope.

No specific period is provided

The embankment time can be some how linked to the consolidation of the subsoil based on pwp dissipation. Instrumentation can help in this situation- pneumatic piezometers. For the slope case you may wish to explore the unsaturated soil mechanics end.


"Data speak for themselves" -Reverend Thomas Bayes 1702-1761
P(Ai|E)=(P(E|Ai)P(Ai))/P(E)